Waurn Ponds Stabling Yards

Waurn Ponds Stabling Yards
PROJECT OVERVIEW

Delivery of major civil, rail and supporting infrastructure works to expand stabling capacity on Victoria's Geelong rail line.

Scope

Keystone Civil was engaged by Downer Engineering to deliver extensive civil construction, earthworks, utility services and shared user pathway infrastructure for the Waurn Ponds Stabling Yards project. Delivered as part of the Regional Rail Revival program, the project supports improvements to the Geelong line, one of Victoria's busiest regional rail corridors.

The initial stage involved bulk earthworks and subgrade preparation, including the placement of approximately 120,000 tonnes of imported fill over three months. Works also included construction of a retention basin, installation of two SPEL oil-water separation units, stormwater drainage infrastructure and road and rail drainage crossings to manage surface water and protect the surrounding environment.

Subsequent works included service trenching, communications infrastructure, rail ballast installation, pavement construction and concrete works. Keystone also delivered fuel spill containment and refuelling pads, asphalt pavements, road line marking, signage and hydroseeding. Additional works included approximately 500 metres of shared user pathway, incorporating kerb construction, solar lighting, drainage and swales to connect Waurn Ponds Station with the Armstrong Creek network.

Keystone also completed two additional rail occupations involving the removal and replacement of approximately 300 metres of existing rail ballast and formation, improving the supporting infrastructure for rail operations.

Project Delivery

Delivered over approximately 18 months, the project required careful staging and coordination with Downer Engineering and multiple specialist contractors working across an active rail construction environment. Keystone implemented environmental controls to manage runoff, sediment and potential fuel contamination while prioritising resource recovery and sustainable material management.

Approximately 4,000 tonnes of recycled concrete and crushed rock and 3,000 tonnes of recycled glass were incorporated into construction activities, reducing reliance on virgin materials. In addition, a significant volume of excavated rock was transported to Boral for crushing and processing into engineered fill for beneficial reuse, diverting material from disposal and supporting circular construction practices.

Coordinated programming and resource management also enabled completion of the shared user pathway within a four-week timeframe to meet the station opening milestone.

‍

PROJECT SUMMARY

Built on experience. Ready for what’s next.

Delivery of bulk earthworks, rail infrastructure, drainage, utility services and shared pathways to support expanded stabling capacity on the Geelong rail line.

Overview

Client

Downer Group

Completion

2023

Major Earthworks & Rail Infrastructure

Placement of 120,000 tonnes of imported fill, construction of rail formation and ballast, and installation of supporting drainage and utility infrastructure.

‍

Sustainable Construction Practices

Reuse of 4,000 tonnes of recycled concrete and crushed rock and 3,000 tonnes of recycled glass, supported by comprehensive sediment and runoff controls.

‍

PROJECTS
Keystone Civil project site photo
Landfills & Environmental
Bulk Earthworks

Anglesea Landfill Cell Capping

Anglesea Landfill Cell Capping

Keystone Civil project site photo
Roads & Transport
Civil Infrastructure

Deakin University Burwood Carpark

Deakin University Burwood Carpark

Keystone Civil project site photo
Water & Wastewater Infrastructure
Landfills & Environmental

Highton Basin Cover & Liner Replacement

Highton Basin Cover & Liner Replacement